Hogan Lovell OffshoreBook 2023 230809 OnlinePDF - Flipbook - Page 196
196
Poland
The estimated investment is worth more
than EUR 150 million, and production is
scheduled to start in 202517 Vestas has also
decided to invest in Poland, and it intends to
locate a new factory for offshore wind farm
17 18 19
, ,
OWF PROJECT
With location permits
AREA
GRID CONNECTION
1
Polenergia/Equinor –
Bałtyk I
128 km2
1,560 MW
(GCA)
2
Polenergia/Equinor –
Bałtyk II
122 km2
720 MW
(GCA)
3
Polenergia/Equinor –
Bałtyk III
120 km2
4
PGE Baltica 2 / Ørsted
5
turbine components in Szczecin. The factory
is expected to begin operations in the second half of 2024 and will supply manufactured components to both Polish and global
offshore markets.18
ENVIRONMENTAL DECISION
CfD
European
Commision’s
Decision
NO
N/A
YES (2017) connection
infrastructure - suspended proceedings pending submission
of report
YES
(2021)
pending
720 MW
(GCA)
YES (2016) and changed in 2022
connection infrastructure - suspended proceedings pending
submission of report
YES
(2021)
pending
189 km2
1,498 MW
(GCA)
YES (2020) connection infrastructure – YES (2022)
YES
(2021)
YES
(2022)
PGE Baltica 3 / Ørsted
131 km2
1,045 MW
(GCA)
YES (2020) connection infrastructure – YES (2022)
YES
(2021)
YES
(2022)
6
PGE Baltica 1
108 km2
896 MW
(GCA)
NO
N/A
7
BTI-RWE Renewables
42 km2
350 MW
(GCA)
YES (2021) connection infrastructure – in progress
YES
(2021)
pending
8
PKN Orlen / Northland
– Baltic Power
131 km2
1,1197 MW
(GCA)
pending proceedings to amend
the decision issued in 2022
YES
(2021)
pending
9/10
Ocean Winds (EDPR/
Engie) BC-
90 km2
369 MW
(GCC)
YES (2022)
YES
(2021)
pending
11
Baltex 2 (unpaid
permit)
Early stage
66 km2
800 MW
NO
N/A
12
Baltex 5 (unpaid
permit)
cancelled
111 km2
1,500 MW
NO
N/A
1,238
km2
10,655 MW
TOTAL
17 Source: https://offshore.cire.pl/artykuly/serwis-informacyjny-cire-24/zawarto-umowe-ws-budowy-fabryki-wiez-dla-morskiej-energetykiwiatrowej (in Polish only)
18 Source: https://www.balticpower.pl/aktualnosci/morska-farma-wiatrowa-baltic-power-nap%C4%99dza-nowe-inwestycje/ (in Polish only)
19 GCC – Grid Connection Conditions; GCA – Grid Connection Agreement; CfD – projects granted support under an individual decision by ERO in 2021
(Phase I); other projects potentially to be covered by auctions starting from 2025 (Phase II)