Offshore Wind Worldwide 2022 edition - Flipbook - Page 146
146
Hogan Lovells
Japan
Annex 1
Project implementation capability
(80 points)
Evaluation item
Viewpoint of confirmation
Method of confirmation
Steady
implementation
of the project
Project performance
Has experience in the installation,
maintenance and operation of offshore
wind power generation facilities, or has
experience in the installation,
maintenance and operation of onshore
wind power generation facilities and
marine civil engineering work
Feasibility of the business plan
Specificity, feasibility, and reliability of
schedules, plans for the marine
renewable energy power generation
facilities, construction plans,
maintenance and management plans,
and income and expenditure plans
Identification and analysis of risks
Have the risks that may lead to business
withdrawal been analyzed, and are
responses possible?
• R
isks related to construction (e.g.,
appropriate manufacturers, ships
installed, presence or absence of
specific installation equipment,
Impact of infectious diseases on
construction schedule, etc.)
aintenance risks (technical
• M
impediments, Impact of shortage
of engineers due to infectious
diseases, etc.)
• R
isks related to financial
management (responses to
fluctuations in wind conditions)
Appropriateness of financial plans
(financial plans, income and
expenditure plans)
Confirm financial plans (financial plans,
income and expenditure plans), etc.