Offshore Wind Worldwide 2022 edition - Flipbook - Page 58
58
Hogan
Lovells
Denmark
recent tender for Thor OWF resulting in bids
at the minimum price.2
OWF
Tender date
Feed in tariff
Horns Rev 2
7 July 2004
DKK 0.518 per kWh (approx. EUR 0.07)
Rødsand 2
7 February 2008
DKK 0.629 per kWh (approx. EUR 0.08)
Anholt
30 April 2009
DKK 1.051 per kWh (approx. EUR 0.14)
Horns Rev 3
6 December 2013
DKK 0.77 per kWh (approx. EUR 0.10)
Kriegers Flak
22 December 2016
DKK 0.372 per kWh (approx. EUR 0.05)
Thor
1 December 2021
DKK 0.01 per kWh (approx. EUR 0.0013)
B.Consequences of
a project delay
If the developer does not meet the deadline
in the concession agreement for connecting
to the grid (tender process OWF), it may
incur a significant amount of liquidated
damages. The liability system is usually set
out in a concession agreement for the
specific project.
V. Grid and grid connection
C.Examples of
actual and future tariffs
As described above, feed in tariffs for the
OWFs which have been tendered are settled
in each tender. Therefore, the feed in tariffs
vary. Examples of tariffs from previous
tenders are set out in the table above.
B.Responsibility for the cost of
the grid connection system
The developer must cover Energinet’s costs
for the construction of the onshore GCS.
2
A.Planning and construction
of the grid connection system
Energinet is responsible for constructing and
operating the GCS from the onshore
substation to the overall transmission grid,
while the offshore substation and export
cables are within the scope of the tender.
C.Consequences of delays and
disruptions of the
grid connection system
If Energinet does not meet the deadlines and
comply with conditions for grid connection
of the OWF according to the terms of the
Political agreement of 4 December 2021, Investments in a consciously greener Denmark, entered into between the government, the
Socialist People’s Party, the Social Liberal Party, the Unity List, the Alternative and Kristendemokraterne.